Heat Recovery System
Case: BillerudKorsnäs, Skärblacka: PM9 air system rebuild.
Goals
The BillerudKorsnäs Skärblacka PM9 machine hall ventilation system needed updating. The amount of supply air was insufficient. The air balance and working conditions needed a new supply air system and a heat recovery system.
Solution
We provided additional supply air capacity and improved the heat recovery. Furthermore the wet end ventilation system was rebuilt.
Wet end ventilation.
How it works
Heat and humidity load is reduced by using more efficient air systems.
Timetable
The ventilation system was rebuilt in two separate projects in 2014-2015: First were machine hall supply air units rebuilt, and after that were the heat recovery system and exhaust air units rebuilt.
Results
- Provided ideal working conditions for the personnel.
- Low operating costs due to a modern and efficient heat recovery system.
- Longer lifespan for the building due to efficient ventilation.